IMPORTANT KRT 150 to KRT 540 Wood Fired Boiler Maximum output: 150 to 540 kW / 5
10 and regulations) these being separate items for the scope of delivery ordered from Viessmann according to the de-scriptio
11 8.3 Inspection of the installation Before the commissioning, the future operating organisa-tion along with the installing companie
12 Notes
a) Note: - To reliably prevent boiler corrosion caused by condensation of flue gases, the boiler return flow temperature must not under
Mixing valves: North America boiler model 3-way mixing valve mixing valve actuator KRT- Viessmann Viessmann diameter part no. part
a) Fire-extinguishing System for Burner Slide-in Module, Art. No. K-SLE Note: Pyromat-DYN has an extra charge with Art. No. K-SLE (see Sp
Spec Sheet Fire- extinguishing Systems K-SLE & K-SLV Installation vIESmAnn 4550-2
Spec Sheet Fire- extinguishing Systems K-SLE & K-SLV Installation vIESmAnn 4550-3
Description: The PYROT Rotation Heating System (patent no: EP 0 905 442 B1) was developed for automatic incineration of all dry to moist wo
2 Safety, Installation and Warranty Requirements Please ensure that’ these instructions are read and understood before commencing installation. F
Technical specs: PYROT Rotation Heating system Trade name 150 220 300 400 540 Item No: KRT-150 KRT-220 KRT-300 KRT-400 KRT-540 Perfor
Spec Sheet Pyrot Rotation Heating System Boiler Plant vIESmAnn 6010-3
Connections / dimensions: Ptrtec [Item-Nr.] KRT-150 KRT- 220 KRT-300 KRT-400 KRT-540 Water connection PN 6 (see Spec Sheet 6960) l B
Description: Exhaust gas de-duster 90 liters [24 USG], [Item no. KRT-E…-1] The exhaust gas de-duster is for minimizing dust emissions an
Dimensions and data: Exhaust flue gas de-duster PYROT [ITEM NO] KPR-E150-1 KPR-300-1 KPR-E400-1 KPR-E540-1 A [in] / [mm] 7.9 / 20
Description: De-ashing in Ash Bin 240 liters [63.5 USG], [Item No. KRT-A2-S] De-ashing in Ash Skip, 800 liters [211.3 USG], [Item No. KRT
Description: De-ashing in Base Container [Item No. KRT-ES-100-S] De-ashing in Base Container [Item No. KRT-ES-150-S] De-ashing in Base Co
Description: Pneumatic Cleaning System [Item No. KRT-W100-S] Pneumatic Cleaning System [Item No. KRT-W150-S] Pneumatic Cleaning System [I
PYROT – Vitocontrol-C A microprocessor control system for the complete PYROT Boiler Plant, incl. control of the systems for the fuel loadi
Extensions available for the PYROT Vitocontrol-C Control System (Article ECO-…) at an extra charge: PYROT Single-unit System: Designatio
Safety, Installation and Warranty Requirements Fiberglass wool and ceramic fiber Materials The state of California has listed the airborne fiber
Triggering System for external drive [Art. No. ECO-A10] Function: Starttec motor starter for optimized connection of an external conveyor
Note: The control system components below are reserved for the PYROT Single-unit System. With the PYROT Double-unit System, these function
Mastercontrol [Art. No. ECO-M1] Mastercontrol improves the overall generation of heat by two biomass boilers (PYROT double-unit system), in
Extensions available for the Mastercontrol (article ECO-M1) at an extra charge: Designation
Control Module with Extended Control System [Art. No. ECO-BM-00] The ECOTRONIC is a decentralized microprocessor system in which various
Controller for Heat Generator, single [Art. No. ECO-KE] Immediately after heat is taken from the accumulator to cover a heat requirement
Parallel heat generator control [Art.-No.: ECO-KP0] The additional heat generator designed as a hydraulic switch supplies heat to the s
Controller for Room Heating Units [Art. No. ECO-H] A weather-guided heating control system with a digital timer for lower able operation a
Controller for Air Handling Unit Group [Art. No. ECO-L] The burner storage system supplies the air heaters with maximum flow temperature.
Controller for Solar Domestic Water Heater [Art. No. ECO-S1] For use in simple solar facilities as a single control circuit for heating t
4 Contents 1 General Information 6 1.1 State of the art 6 1.2 Documented information 6 2 Codes 6 2.1 M
Spec Sheet ECOTRONIC Heating Control Unit Solar Energy vIESmAnn 4050-2
Visualization of Pyromat Internally [ECO-VIM] Visualization of Pyrot Internally [ECO-VIR] All the data is conducted to the PC by a data t
Arrangement of the electrical wiring on the Pyrot (Recommendation for the electrician; not included in the scope of delivery) vIESmAnn 1/
Installation (one fitter with helper provided by the customer) [Art. No. IMO-1] Performance provided by the contractor (supplier): Furni
Installation (two KÖB fitters) [Art. No. IMO-2] Performance provided by the contractor (supplier): Furnishing the entire scope of the de
A prerequisite for approval is the express permission for such by the public authority responsible. For claims to the warranty according to
5) Bulk density S (kg/m³), water content W (%), size G (mm) Bulk density S in kg/m³ (lb/ft3), water content W in %, size C1, C3,
Attachment B TERMS AND CONDITIONS OF SALE, DELIVERY AND PAYMENT GENERAL PROVISIONS 1. (a) This agreement, performances of contract and quot
5302 630 08/08 Printed in Canada sold and delivered and to seize the same wherever the same may be located at any time of day or night or to
Viessmann Manufacturing Company (U.S.) Inc. 45 Access Road Warwick, Rhode Island 02886 USA Tel. (401) 732-0667 Fax (401) 73
5 9 Spec Sheets 6960-1, 2, 3 PYROT rotary combustion chamber boiler, Installation of Closed System 4550-1, 3 Extinguishing System, I
6 1 General Information Viessmann solid-fuel boiler may only be set up and com-missioned by specialists. This will rule out any incorre
7 3 The structural Surroundings for the Boiler The national building regulations existing in this connection must always be complied with. 3
8 5 Water System Installation Customers must ensure that there is a supply of water in-dependent of the electricity supply. This (redund
9 6 Electrical Installation 6.1 Positioning the control module and control cabinet Electrical company at a place easily accessible for